CDM 2015 · Regulation 12

Health and safety file under CDM 2015

The health and safety file is the information handed to the client at the end of a project so that anyone doing future cleaning, maintenance, alterations or demolition knows about the risks. It's only needed on projects with more than one contractor.

Health and safety file under CDM 2015: preview of the free template

When is a health and safety file needed?

CDM 2015 requires a health and safety file on projects involving more than one contractor. The principal designer prepares it during the pre-construction phase, and it is updated throughout. At the end of the project it is passed to the client. If the principal designer's appointment ends first, the file passes to the principal contractor to finish and hand over.

What to include

Only information that will help someone work safely on the building in future. Typical contents:

  • A brief description of the work carried out.
  • Residual hazards and how they were dealt with: surveys of asbestos, contaminated land, buried services.
  • Key structural principles, such as bracing and safe working loads for floors and roofs.
  • Hazardous materials used, such as lead paint and special coatings.
  • Information about removing or dismantling installed plant and equipment.
  • Equipment for cleaning or maintaining the structure, such as roof anchor points.
  • The nature, location and markings of significant services, including fire-fighting services.
  • As-built drawings of the structure, its plant and equipment.

Keep it short and useful. HSE warns against filling the file with general product brochures or certificates that don't help future work. A thin, relevant file is better than a thick one nobody reads.

Health and safety file contents checklist

HSF-CHK · Rev A
CheckYes / No / N/ANotes
Description of the work carried out
Residual hazards and how they were dealt with
Asbestos and other surveys
Key structural principles and safe working loads
Hazardous materials used
Removal or dismantling of plant and equipment
Cleaning and maintenance equipment (e.g. anchor points)
Location and markings of services
As-built drawings
Handed to client (date)
Free to use. Adapt it to your job before use; a template is a starting point, not a finished assessment.

Health and safety file vs construction phase plan

Construction phase planHealth and safety file
PurposeManaging risks during the buildInformation for future work on the building
Who writes itPrincipal contractor or contractorPrincipal designer
When neededEvery projectProjects with more than one contractor
Who keeps itSite team, during the jobThe client, for the life of the building

Frequently asked questions

Who is responsible for the health and safety file?

The principal designer prepares, reviews and updates it. The client must keep it and make it available to anyone who needs it for future work.

Is a health and safety file needed for a single contractor job?

No. CDM 2015 only requires a health and safety file where there is more than one contractor on the project.

How long should the client keep the health and safety file?

For the life of the building, and pass it on if the building is sold.

Sources

This guide is written from the legislation and HSE guidance below. Last checked 23 October 2026.